Tennessee Gas Pipeline Icon

RESTRICTIONS FOR 03-19-2025 ID2

Tennessee Gas Pipeline 1mo ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  03/19/2025 3:58:35PM Notice End Date/Time:  03/20/2025 9:00:00am
Post Date/Time:  3/19/2025 3:58:35 PM Notice ID: 394073
Reqrd Rsp:  1 Rsp Date:  03/19/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 03-19-2025 ID2
Notice Text:

Effective Intraday 2 Cycle (18:00) for the gas day of Wednesday, March 19, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR ZONES L AND 1 ON THE 500 LINE ONLY (SEGMENTS 527, 529, 530, 534, 539, 542, 548, 860) FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES

 

METER RESTRICTIONS

·         GDR/TGP Rio Bravo Hidalgo Delivery Meter (Pin 421017) - through 100% of PIP increases deliveries due to location off rate; 53,802 Dths

·         Tres Palacios /TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss increases due to imbalance management quantity exceeded; 80,000 Dths

·         TRANSCO/TGP Kinder La Exch (Bi 1 Delivery Meter (Pin 420373) - through 100% of SOP increases due to operational concerns; 4,889 Dths

·         TRANSCO/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths

SEGMENT RESTRICTIONS

·         STA 40 South Of Carthage (Segment 132 FH) - through 100% of SOP increases due to emergent repair at STA 40;  10,522 Dths

·         STA 860 (Segment 860 BH) - through 100% of SOP increases due to force majeure at STA 860; 1,324 Dths

·         STA 110 South (Segment 187 BH) - through 100% of SOP increases due to emergent repair between STA 96-1 to MLV 101-1; 9,983 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 252,887 Dths

·         MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 346,048 Dths

·         STA 224 (Segment 224 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 50,834 Dths

·         Z5 HC North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 222,574 Dths

·         STA 245 (Segment 245 FH) - through approx 95% of SOP increases due to nominations in excess of operational capacity; 273,170 Dths

·         MLV 273 (Segment 284 FH) - through approx 93% of SOP increases due to nominations in excess of operational capacity; 113,331 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

STORAGE RESTRICTIONS

NONE

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  03/19/2025 3:58:35PM Notice End Date/Time:  03/20/2025 9:00:00am
Post Date/Time:  3/19/2025 3:58:35 PM Notice ID: 394073
Reqrd Rsp:  1 Rsp Date:  03/19/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 03-19-2025 ID2
Notice Text:

Effective Intraday 2 Cycle (18:00) for the gas day of Wednesday, March 19, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR ZONES L AND 1 ON THE 500 LINE ONLY (SEGMENTS 527, 529, 530, 534, 539, 542, 548, 860) FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES

 

METER RESTRICTIONS

·         GDR/TGP Rio Bravo Hidalgo Delivery Meter (Pin 421017) - through 100% of PIP increases deliveries due to location off rate; 53,802 Dths

·         Tres Palacios /TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss increases due to imbalance management quantity exceeded; 80,000 Dths

·         TRANSCO/TGP Kinder La Exch (Bi 1 Delivery Meter (Pin 420373) - through 100% of SOP increases due to operational concerns; 4,889 Dths

·         TRANSCO/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths

SEGMENT RESTRICTIONS

·         STA 40 South Of Carthage (Segment 132 FH) - through 100% of SOP increases due to emergent repair at STA 40;  10,522 Dths

·         STA 860 (Segment 860 BH) - through 100% of SOP increases due to force majeure at STA 860; 1,324 Dths

·         STA 110 South (Segment 187 BH) - through 100% of SOP increases due to emergent repair between STA 96-1 to MLV 101-1; 9,983 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 252,887 Dths

·         MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 346,048 Dths

·         STA 224 (Segment 224 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 50,834 Dths

·         Z5 HC North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 222,574 Dths

·         STA 245 (Segment 245 FH) - through approx 95% of SOP increases due to nominations in excess of operational capacity; 273,170 Dths

·         MLV 273 (Segment 284 FH) - through approx 93% of SOP increases due to nominations in excess of operational capacity; 113,331 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

STORAGE RESTRICTIONS

NONE

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.