Maint.Update #2 - N. Main Loop Seg 130
Southern Natural Gas 1mo ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Update
to Scheduled Pipeline Maintenance – North Main loop line east of Providence
(Segment 130 – Tarrant) Update #2
The scheduled pipeline maintenance on the North Main loop line east of
Providence compressor station (Segment 130 – Tarrant) located in Jefferson
County, AL, referenced on Southern's weekly EBB maintenance postings and
posting (#712277) posted on August 12, 2026, scheduled from July 6, 2026, to August
21, 2026, remains on-going and has been extended through August 24, 2026.
Additionally, the scheduled pipeline maintenance on the North Main loop line
east of Tarrant compressor station (Segment 130 – Tarrant) located in Jefferson
County, AL referenced on Southern's weekly EBB maintenance postings scheduled
from August 19, 2026, to August 30, 2026, has been rescheduled to August 24,
2026, through September 4, 2026. As a result, Segment 130 (Tarrant) capacity of
563 Mdth/d will remain impacted by 125 Mdth/d through gas day, Monday August 24, 2026. Effective
Timely Cycle, gas day Tuesday, August 25, 2026, Segment 130 (Tarrant) capacity of 563 Mdth/d
will be updated to reflect a reduced impact of 25 Mdth/d through gas day, Friday, September 4,
2026. Based on current
system demand, an impact to Interruptible and Out of Path nominations may
become necessary
Please continue to reference our weekly EBB postings for current maintenance information. If you have any questions, please contact your Scheduling Representative or Account Manager.
SNG Gas Control
Update
to Scheduled Pipeline Maintenance – North Main loop line east of Providence
(Segment 130 – Tarrant) Update #2
The scheduled pipeline maintenance on the North Main loop line east of
Providence compressor station (Segment 130 – Tarrant) located in Jefferson
County, AL, referenced on Southern's weekly EBB maintenance postings and
posting (#712277) posted on August 12, 2026, scheduled from July 6, 2026, to August
21, 2026, remains on-going and has been extended through August 24, 2026.
Additionally, the scheduled pipeline maintenance on the North Main loop line
east of Tarrant compressor station (Segment 130 – Tarrant) located in Jefferson
County, AL referenced on Southern's weekly EBB maintenance postings scheduled
from August 19, 2026, to August 30, 2026, has been rescheduled to August 24,
2026, through September 4, 2026. As a result, Segment 130 (Tarrant) capacity of
563 Mdth/d will remain impacted by 125 Mdth/d through gas day, Monday August 24, 2026. Effective
Timely Cycle, gas day Tuesday, August 25, 2026, Segment 130 (Tarrant) capacity of 563 Mdth/d
will be updated to reflect a reduced impact of 25 Mdth/d through gas day, Friday, September 4,
2026. Based on current
system demand, an impact to Interruptible and Out of Path nominations may
become necessary
Please continue to reference our weekly EBB postings for current maintenance information. If you have any questions, please contact your Scheduling Representative or Account Manager.
SNG Gas Control