-Restrictions to Primary In-Path transportation services may be necessary.
|
|
|
SNG - Outage
Impact Report
|
|
|
-Restrictions to In-Path transportation services may be necessary.
|
|
September
2025 (updated 08/21/25)
|
|
-Restrictions to Interruptible and Out of Path transportation services may be necessary.
|
-No anticipated impact to transportation services.
|
Station / Seg
|
Est Nominal Design Capacity (Thousand Dth)
|
Week 1 (9/1 - 9/7)
|
Week 2 (9/8 - 9/14)
|
Week 3 (9/15 - 9/21)
|
Week 4 (9/22 - 9/28)
|
Primary
Outage(s)
|
Est. Operational Capacity (Operational Impact) - Thousand Dth
|
Onward (segment 30)
|
203
|
178
(25)
|
203
|
203
|
203
|
North Main 2nd loop line west
of Onward: Scheduled Pipeline Maintenance(PT), Proj-SNG-15323 (7/22/2025 - 9/5/2025)
|
Louisville East
(segment 50)
|
520
|
520
|
520
|
520
|
360
(160)
|
Louisville Compressor Station: Scheduled Unit
Maintenance, Proj-4132LS (9/22/2025 - 9/26/2025)
|
Duncanville Lateral (segment 90)
|
36
|
36
|
36
|
36
|
36
|
|
Providence (segment 120)
|
652
|
527
(125)
|
652
|
652
|
652
|
North Main
loop line west of Tarrant: Pipeline Maintenance(remediation),
Proj-SNG-38814 (8/21/2025 - 9/4/2025)
|
Dearmanville (segment 150)
|
346
|
346
|
346
|
346
|
346
|
|
White Castle
(segment 340)
|
772
|
772
|
707
(65)
|
707
(65)
|
707
(65)
|
Duck Lake
Franklinton line south of White Castle: Scheduled Pipeline
Maintenance(remediation), Proj- SNG-20777 (9/8/2025 - 10/6/2025)
|
LA West Leg (segment 350)
|
695
|
695
|
695
|
675
(20)
|
675
(20)
|
Duck
Lake Franklinton Line
north of White Castle: Pipeline Maintenance, Proj-SNG-2933
(9/15/2025 - 9/30/2025)
|
Sesh (segment 380)
|
500
|
500
|
500
|
500
|
500
|
|
Gwinville (segment 400)
|
234
|
234
|
234
|
234
|
234
|
|
Bay Springs (segment 420)
|
1,675
|
1595
(80)
|
1595
(80)
|
1595
(80)
|
1595
(80)
|
Bay Springs Compressor Station: Scheduled Unit Maintenance, Proj-52161 (7/8/2025 - 10/31/2025)
|
Enterprise (segment 430)
|
2,306
|
2111
(195)
|
2111
(195)
|
2111
(195)
|
2111
(195)
|
Enterprise Compressor Station: Scheduled Unit Maintenance, Proj-522212 (9/22/2025 - 10/19/2025) Enterprise Compressor Station: Unscheduled Unit Maintenance, Proj-522211 (6/5/2025 - 9/21/2025) Enterprise Compressor Station: Unscheduled Unit Maintenance, Proj-522211 (7/8/2025 - 9/21/2025)
|
York (segment 440)
|
2,305
|
2,305
|
2080
(225)
|
2,305
|
2,305
|
York Compressor Station: Scheduled Unit
Maintenance, Proj-52303 (9/8/2025 - 9/9/2025)
|
Selma (segment 460)
|
2,293
|
2158
(135)
|
2,293
|
2,293
|
2,293
|
South Main
2nd Loop Line
east of Selma: Scheduled Pipeline Maintenance, Proj-SNG-8793 (8/20/2025 - 9/5/2025)
|
Elmore (segment 460)
|
2,010
|
2,010
|
1850
(160)
|
1735
(275)
|
1735
(275)
|
Auburn Compressor Station: Scheduled Unit Maintenance,
Proj-52591 (9/15/2025 - 9/26/2025) Elmore Compressor Station: Scheduled
Unit Maintenance, Proj-525112 (9/15/2025
- 9/26/2025) South Main
2nd loop line
east of Auburn: Scheduled Pipeline Maintenance(remediation), Proj-SNG- 35931
(9/8/2025 - 9/26/2025)
|
Ellerslie (segment 490)
|
1,547
|
1,547
|
1,547
|
1,547
|
1,547
|
|
Thomaston West (segment 490)
|
1,535
|
1,535
|
1,535
|
1515
(20)
|
1,535
|
Thomaston Compressor Station: Scheduled Unit
Maintenance, Proj-52723-4 (9/15/2025 - 9/18/2025)
|
South Atlanta (segment 510)
|
522
|
522
|
522
|
522
|
522
|
|
Thomaston East
(segment 530)
|
849
|
849
|
849
|
849
|
849
|
|
East/South Wrens (segment 560)
|
680
|
680
|
680
|
585
(95)
|
680
|
Wrens Compressor Station: Scheduled Unit
Maintenance, Proj-52884 (9/15/2025 - 9/19/2025)
|
South Georgia (segment 650)
|
127
|
127
|
127
|
127
|
127
|
|
This document is updated on a weekly basis and outage schedules/impacts are subject to change as the
week progresses.
Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.
The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.
|