Planned Service Outage - May 5th, 2026
Southern Star Central Gas Pipeline 11h ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP: 007906233
Notice ID: 11131
Critical: Y
Notice Type Desc: Planned Service Outage
Notice Stat Desc: Supersede
Prior Notice: 11127
Notice Eff Date Time: 05/05/2026 08:58 am
Notice Eff End Date Time: None
Post Date Time: 05/05/2026 08:58 am
Subject: Planned Service Outage - May 5th, 2026
Notice Text
Southern Star’s 2026 “Planned Service Outage” has been posted to the “Notices” area under the Planned Service Outage category and includes upcoming planned maintenance scheduled for this year. Changes to this schedule are always possible and will be posted to the bulletin board as soon as firm dates are known.
Revised (2)
- The Pipeline Reconfirmation in the Edmond CS has been updated with new dates. The PSO will now take place May 27th, 2026, and return to service May 28th, 2026. The locations impacted will be: 0 dth/d Edmond CS w/o OK (location:449003).
- The Pipeline Reconfirmation in the Edmond CS has been updated with new dates. The final tie in will take place June 17th, 2026, and return to service June 18th, 2026. The location impacted will be: 0 dth/d Edmond CS w/0 OK (location: 449003).
The PSO Dashboard provides an interactive way to find and filter information related to the PSO items.
PSO Dashboard link: Planned Service Outage
PSO PDF: PSO
Scott Warren Office: 270.852.4559 Cell: 270.302.6433
Buster Ashley Office: 270.852.4546 Cell: 270.314.1436
TSP: 007906233
Notice ID: 11131
Critical: Y
Notice Type Desc: Planned Service Outage
Notice Stat Desc: Supersede
Prior Notice: 11127
Notice Eff Date Time: 05/05/2026 08:58 am
Notice Eff End Date Time: None
Post Date Time: 05/05/2026 08:58 am
Subject: Planned Service Outage - May 5th, 2026
Notice Text
Southern Star’s 2026 “Planned Service Outage” has been posted to the “Notices” area under the Planned Service Outage category and includes upcoming planned maintenance scheduled for this year. Changes to this schedule are always possible and will be posted to the bulletin board as soon as firm dates are known.
Revised (2)
- The Pipeline Reconfirmation in the Edmond CS has been updated with new dates. The PSO will now take place May 27th, 2026, and return to service May 28th, 2026. The locations impacted will be: 0 dth/d Edmond CS w/o OK (location:449003).
- The Pipeline Reconfirmation in the Edmond CS has been updated with new dates. The final tie in will take place June 17th, 2026, and return to service June 18th, 2026. The location impacted will be: 0 dth/d Edmond CS w/0 OK (location: 449003).
The PSO Dashboard provides an interactive way to find and filter information related to the PSO items.
PSO Dashboard link: Planned Service Outage
PSO PDF: PSO
Scott Warren Office: 270.852.4559 Cell: 270.302.6433