Overrun Entitlement Warning North of Muddy Creek North Constraint
Northwest 1mo ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: PIPELINE CONDITIONS
Post D/T: 08/25/2026 5:02 PM MCT
Notice Eff D/T: 08/25/2026 5:02 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-158
Prior Notice:
Subject: Overrun Entitlement Warning North of Muddy Creek North Constraint
Notice Text:
Due to excessive drafting, Northwest is issuing an Overrun
Entitlement Warning for all Receiving Parties north of the Muddy
Creek North Constraint beginning Gas Day Thursday, August 27,
2026 until further notice.
As a reminder and pursuant to Section 14.6(c) of its Tariff,
customer-specific entitlements may be issued to Receiving
Parties that:
1) has contributed to the adverse operating conditions for at
least two consecutive days; and
2) whose actual measured deliveries have deviated from
scheduled deliveries for the previous Gas Day by the greater of
10,000 Dth or 5 percent.
Please remain diligent in managing supply and demand and avoid
drafting the system. Off system balancing on Northwest’s
Electronic Bulletin Board is currently designated as “No” for all
areas.
If you have any questions, please contact your Commercial
Services Representative or the Scheduling Hotline at 713-215-
6301.
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: PIPELINE CONDITIONS
Post D/T: 08/25/2026 5:02 PM MCT
Notice Eff D/T: 08/25/2026 5:02 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-158
Prior Notice:
Subject: Overrun Entitlement Warning North of Muddy Creek North Constraint
Notice Text:
Due to excessive drafting, Northwest is issuing an Overrun
Entitlement Warning for all Receiving Parties north of the Muddy
Creek North Constraint beginning Gas Day Thursday, August 27,
2026 until further notice.
As a reminder and pursuant to Section 14.6(c) of its Tariff,
customer-specific entitlements may be issued to Receiving
Parties that:
1) has contributed to the adverse operating conditions for at
least two consecutive days; and
2) whose actual measured deliveries have deviated from
scheduled deliveries for the previous Gas Day by the greater of
10,000 Dth or 5 percent.
Please remain diligent in managing supply and demand and avoid
drafting the system. Off system balancing on Northwest’s
Electronic Bulletin Board is currently designated as “No” for all
areas.
If you have any questions, please contact your Commercial
Services Representative or the Scheduling Hotline at 713-215-
6301.
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: PIPELINE CONDITIONS
Post D/T: 08/25/2026 5:02 PM MCT
Notice Eff D/T: 08/25/2026 5:02 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-158
Prior Notice:
Subject: Overrun Entitlement Warning North of Muddy Creek North Constraint
Notice Text:
Due to excessive drafting, Northwest is issuing an Overrun
Entitlement Warning for all Receiving Parties north of the Muddy
Creek North Constraint beginning Gas Day Thursday, August 27,
2026 until further notice.
As a reminder and pursuant to Section 14.6(c) of its Tariff,
customer-specific entitlements may be issued to Receiving
Parties that:
1) has contributed to the adverse operating conditions for at
least two consecutive days; and
2) whose actual measured deliveries have deviated from
scheduled deliveries for the previous Gas Day by the greater of
10,000 Dth or 5 percent.
Please remain diligent in managing supply and demand and avoid
drafting the system. Off system balancing on Northwest’s
Electronic Bulletin Board is currently designated as “No” for all
areas.
If you have any questions, please contact your Commercial
Services Representative or the Scheduling Hotline at 713-215-
6301.
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: PIPELINE CONDITIONS
Post D/T: 08/25/2026 5:02 PM MCT
Notice Eff D/T: 08/25/2026 5:02 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 26-158
Prior Notice:
Subject: Overrun Entitlement Warning North of Muddy Creek North Constraint
Notice Text:
Due to excessive drafting, Northwest is issuing an Overrun
Entitlement Warning for all Receiving Parties north of the Muddy
Creek North Constraint beginning Gas Day Thursday, August 27,
2026 until further notice.
As a reminder and pursuant to Section 14.6(c) of its Tariff,
customer-specific entitlements may be issued to Receiving
Parties that:
1) has contributed to the adverse operating conditions for at
least two consecutive days; and
2) whose actual measured deliveries have deviated from
scheduled deliveries for the previous Gas Day by the greater of
10,000 Dth or 5 percent.
Please remain diligent in managing supply and demand and avoid
drafting the system. Off system balancing on Northwest’s
Electronic Bulletin Board is currently designated as “No” for all
areas.
If you have any questions, please contact your Commercial
Services Representative or the Scheduling Hotline at 713-215-
6301.