Force Majeure: St Anthony Compressor 7
Northern Border Pipeline Company 4w ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TSP Name
Northern Border Pipeline Company
TSP
021632583
Date
Time
Notice ID
26245010
Notice Type Description: Force Majeure
Notice Stat Desc: Initiate
Prior Notice:
Critical: Y
Reqrd Rsp Desc: No Response Required
Post
Notice Effective
Notice End
Response
09/10/26
09/10/26
10/10/26
7:14:41 PM
4:00:00 AM
4:00:00 AM
Subject: Force Majeure: St Anthony Compressor 7
Author: Kyle Krigbaum
Notice Text
Northern Border Pipeline Company (NBPL) notifies customers of the need to perform work to address an unplanned and uncontrollable equipment failure at Compressor Station 07 (CS07). This necessary measure could not be prevented or overcome by the due diligence of NBPL and requires immediate action to maintain the safety and reliability of the system. Therefore, pursuant to Section 6.9.1 of the General Terms and Conditions of NBPL’s FERC Gas Tariff, NBPL is declaring a Force Majeure effective, Friday, September 11, 2026. As a result of the Force Majeure, NBPL will restrict nominated volumes for Flow Past Glen Ullin (GlenSEG) to 2,160 MMcf/d (2,322,875 Dth) effective Evening, September 11, 2026, and continuing until further notice. Reservation Charge Credits, if necessary, will be provided consistent with Section 6.6.7 of NBPL's Tariff. NBPL will provide updates as additional information becomes available. If you have any scheduling or nominations questions, please call your Northern Border Customer Services Representative at (866) 581-6487.
Northern Border Pipeline Company
TSP
021632583
Date
Time
Notice ID
26245010
Notice Type Description: Force Majeure
Notice Stat Desc: Initiate
Prior Notice:
Critical: Y
Reqrd Rsp Desc: No Response Required
Post
Notice Effective
Notice End
Response
09/10/26
09/10/26
10/10/26
7:14:41 PM
4:00:00 AM
4:00:00 AM
Subject: Force Majeure: St Anthony Compressor 7
Author: Kyle Krigbaum
Notice Text
Northern Border Pipeline Company (NBPL) notifies customers of the need to perform work to address an unplanned and uncontrollable equipment failure at Compressor Station 07 (CS07). This necessary measure could not be prevented or overcome by the due diligence of NBPL and requires immediate action to maintain the safety and reliability of the system. Therefore, pursuant to Section 6.9.1 of the General Terms and Conditions of NBPL’s FERC Gas Tariff, NBPL is declaring a Force Majeure effective, Friday, September 11, 2026. As a result of the Force Majeure, NBPL will restrict nominated volumes for Flow Past Glen Ullin (GlenSEG) to 2,160 MMcf/d (2,322,875 Dth) effective Evening, September 11, 2026, and continuing until further notice. Reservation Charge Credits, if necessary, will be provided consistent with Section 6.6.7 of NBPL's Tariff. NBPL will provide updates as additional information becomes available. If you have any scheduling or nominations questions, please call your Northern Border Customer Services Representative at (866) 581-6487.