Midwestern Gas Transmission Company Icon

Planned Service Outage – MGT Mainline Near Hartford CS #2105 and Perdue Farms

Midwestern Gas Transmission Company 1w ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP: 006792451

TSP Name: Midwestern Gas Transmission Company

Posting Date/Time: 10/01/2026 09:37:15

Notice Identifier: 331

Notice Stat Desc: Initiate

Notice Type Desc: Capacity Constraint

Notice Category: Critical

Subject: Planned Service Outage – MGT Mainline Near Hartford CS #2105 and Perdue Farms

Notice Eff Date/Time: 11/02/2026 09:00:00

Notice End Date/Time: 11/12/2026 09:00:00

Critical Desc: Yes

Notice Scope: TSP SPECIFIC

Reqrd Rsp Desc: No

Response Date/Time:

Prior Notice Identifier:

Notice Text:
Midwestern Gas Transmission Company (MGT) will conduct a planned service outage for a line bore and MAOP project on its mainline. The affected segment is between the Hartford compressor station #2105, and mile post 53 just South the Purdue Farms meter.

Please be advised that full haul transportation will not be available. Nominations will not be accepted for flow through this segment of the pipeline for the duration of the outage.

I. The Perdue Farm meter will be unavailable for Receipt or Delivery during this outage.
II. Flow South of the Hartford CS #2105 will be set to 0 Dth during the outage.
III. Flow North of Perdue Farms meter will be set to 0 Dth during the outage.

Receipts from Portland (Tennessee Gas) can deliver to the South end of the pipe up to and including the Morgantown North meter.
Deliveries to meters north of the outage, including Dundee, must come from points of Receipt north of the affected area


This outage is planned to begin Gas Day Monday, November 2, 2026, Timely Cycle, and is anticipated to be in effect through Gas Day Wednesday, November 11, 2026, Intraday 3 Cycle. The Capacity is anticipated to be reinstated Gas Day Thursday, November 12, 2026, Timely Cycle.

MGT anticipates an impact to Firm Transportation services. Demand charge credits will be applied pursuant to MGT's FERC Gas Tariff, General Terms and Conditions, Section 37.

Please contact your Commercial or Scheduling representative with questions.


TSP: 006792451

TSP Name: Midwestern Gas Transmission Company

Posting Date/Time: 10/01/2026 09:37:15

Notice Identifier: 331

Notice Stat Desc: Initiate

Notice Type Desc: Capacity Constraint

Notice Category: Critical

Subject: Planned Service Outage – MGT Mainline Near Hartford CS #2105 and Perdue Farms

Notice Eff Date/Time: 11/02/2026 09:00:00

Notice End Date/Time: 11/12/2026 09:00:00

Critical Desc: Yes

Notice Scope: TSP SPECIFIC

Reqrd Rsp Desc: No

Response Date/Time:

Prior Notice Identifier:

Notice Text:
Midwestern Gas Transmission Company (MGT) will conduct a planned service outage for a line bore and MAOP project on its mainline. The affected segment is between the Hartford compressor station #2105, and mile post 53 just South the Purdue Farms meter.

Please be advised that full haul transportation will not be available. Nominations will not be accepted for flow through this segment of the pipeline for the duration of the outage.

I. The Perdue Farm meter will be unavailable for Receipt or Delivery during this outage.
II. Flow South of the Hartford CS #2105 will be set to 0 Dth during the outage.
III. Flow North of Perdue Farms meter will be set to 0 Dth during the outage.

Receipts from Portland (Tennessee Gas) can deliver to the South end of the pipe up to and including the Morgantown North meter.
Deliveries to meters north of the outage, including Dundee, must come from points of Receipt north of the affected area


This outage is planned to begin Gas Day Monday, November 2, 2026, Timely Cycle, and is anticipated to be in effect through Gas Day Wednesday, November 11, 2026, Intraday 3 Cycle. The Capacity is anticipated to be reinstated Gas Day Thursday, November 12, 2026, Timely Cycle.

MGT anticipates an impact to Firm Transportation services. Demand charge credits will be applied pursuant to MGT's FERC Gas Tariff, General Terms and Conditions, Section 37.

Please contact your Commercial or Scheduling representative with questions.