REVISED: Planned Service Outage – Flow through Sullivan CS#2113
Midwestern Gas Transmission Company 1mo ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP: 006792451
TSP Name: Midwestern Gas Transmission Company
Posting Date/Time: 06/05/2026 15:18:40
Notice Identifier: 176
Notice Stat Desc: Supersede
Notice Type Desc: Planned Service Outage
Notice Category: Critical
Subject: REVISED: Planned Service Outage – Flow through Sullivan CS#2113
Notice Eff Date/Time: 06/23/2026 09:00:00
Notice End Date/Time: 07/16/2026 09:00:00
Critical Desc: Yes
Notice Scope: TSP SPECIFIC
Reqrd Rsp Desc: No
Response Date/Time:
Prior Notice Identifier: 1525
Notice Text:
Due to planned maintenance between the Sullivan Compressor Station (CS) #2113 and Petersburg CS #2110 Midwestern Gas Transmission Company (MGT) will decrease capacity beginning Gas Day, Tuesday, June 23, 2026, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day, Wednesday, June 24, 2026.
Midwestern Gas Transmission Company (MGT) will again decrease capacity beginning Gas Day, Tuesday, July 14, 2026, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day, Wednesday, July 15, 2026.
Phase 1:
6/23/2026 – 6/24/2026 North bound flow thru Sullivan CS #2113 will be reduced from 544,010dth to 0dth.
6/23/2026 – 6/24/2026 South bound flow thru Sullivan CS #2113 will be reduced from 671,722dth to 160,100dth.
******
6/25/26 – 7/13/26 North bound flow thru Sullivan CS #2113 will be restored to 544,010dth.
6/25/26 – 7/13/26 South bound flow thru Sullivan CS #2113will be restored to 671,722dth.
******
Phase 2:
7/14/2026 - 7/15/2026 North bound flow through Sullivan CS #2113 will be reduced from 544,010dth to 0dth.
7/14/2026 - 7/15/2026 South bound flow through Sullivan CS #2113 will be reduced from 671,722dth to 160,100dth.
MGT does anticipate an impact to firm transportation services. Demand charge credits will be applied pursuant to MGT's FERC Gas Tariff, General Terms and Conditions, Section 37.
Please contact your Commercial or Customer Service representative with questions.
------------------------------------
Prior Notice ID: 171
Due to planned maintenance between the Sullivan Compressor Station (CS) #2113 and the Potomac Compressor Station (CS) #2118, Midwestern Gas Transmission Company (MGT) will decrease capacity beginning Gas Day, Tuesday, June 30, 2026, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day, Wednesday, July 01, 2026. Midwestern Gas Transmission Company (MGT) will again decrease capacity beginning Gas Day, Tuesday, July 14, 2026, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day, Wednesday, July 15, 2026.
Phase 1:
6/30/2026 thru 7/1/2026 North bound flow thru Sullivan CS #2113 will be reduced from 544,010dth to 0dth.
6/30/2026 thru 7/1/2026 South bound flow thru Potomac CS #2218 will be reduced from 540,371dth to 160,100dth.
7/2/2026 thru 7/13/2026 North bound flow thru Sullivan CS #2113 will be restored to 544,010dth.
7/2/2026 thru 7/13/2026 South bound flow thru Potomac CS #2218 will be restored to 540,371dth.
Phase 2:
7/14/2026 thru 7/15/2026 North bound flow thru Sullivan CS #2113 will be reduced from 544,010dth to 0dth.
7/14/2026 thru 7/15/2026 South bound flow thru Potomac CS #2218 will be reduced from 540,371dth to 160,100dth.
MGT does anticipate an impact to firm transportation services. Demand charge credits will be applied pursuant to MGT's FERC Gas Tariff, General Terms and Conditions, Section 37.
Please contact your Commercial or Customer Service representative with questions.
TSP Name: Midwestern Gas Transmission Company
Posting Date/Time: 06/05/2026 15:18:40
Notice Identifier: 176
Notice Stat Desc: Supersede
Notice Type Desc: Planned Service Outage
Notice Category: Critical
Subject: REVISED: Planned Service Outage – Flow through Sullivan CS#2113
Notice Eff Date/Time: 06/23/2026 09:00:00
Notice End Date/Time: 07/16/2026 09:00:00
Critical Desc: Yes
Notice Scope: TSP SPECIFIC
Reqrd Rsp Desc: No
Response Date/Time:
Prior Notice Identifier: 1525
Notice Text:
Due to planned maintenance between the Sullivan Compressor Station (CS) #2113 and Petersburg CS #2110 Midwestern Gas Transmission Company (MGT) will decrease capacity beginning Gas Day, Tuesday, June 23, 2026, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day, Wednesday, June 24, 2026.
Midwestern Gas Transmission Company (MGT) will again decrease capacity beginning Gas Day, Tuesday, July 14, 2026, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day, Wednesday, July 15, 2026.
Phase 1:
6/23/2026 – 6/24/2026 North bound flow thru Sullivan CS #2113 will be reduced from 544,010dth to 0dth.
6/23/2026 – 6/24/2026 South bound flow thru Sullivan CS #2113 will be reduced from 671,722dth to 160,100dth.
******
6/25/26 – 7/13/26 North bound flow thru Sullivan CS #2113 will be restored to 544,010dth.
6/25/26 – 7/13/26 South bound flow thru Sullivan CS #2113will be restored to 671,722dth.
******
Phase 2:
7/14/2026 - 7/15/2026 North bound flow through Sullivan CS #2113 will be reduced from 544,010dth to 0dth.
7/14/2026 - 7/15/2026 South bound flow through Sullivan CS #2113 will be reduced from 671,722dth to 160,100dth.
MGT does anticipate an impact to firm transportation services. Demand charge credits will be applied pursuant to MGT's FERC Gas Tariff, General Terms and Conditions, Section 37.
Please contact your Commercial or Customer Service representative with questions.
------------------------------------
Prior Notice ID: 171
Due to planned maintenance between the Sullivan Compressor Station (CS) #2113 and the Potomac Compressor Station (CS) #2118, Midwestern Gas Transmission Company (MGT) will decrease capacity beginning Gas Day, Tuesday, June 30, 2026, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day, Wednesday, July 01, 2026. Midwestern Gas Transmission Company (MGT) will again decrease capacity beginning Gas Day, Tuesday, July 14, 2026, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day, Wednesday, July 15, 2026.
Phase 1:
6/30/2026 thru 7/1/2026 North bound flow thru Sullivan CS #2113 will be reduced from 544,010dth to 0dth.
6/30/2026 thru 7/1/2026 South bound flow thru Potomac CS #2218 will be reduced from 540,371dth to 160,100dth.
7/2/2026 thru 7/13/2026 North bound flow thru Sullivan CS #2113 will be restored to 544,010dth.
7/2/2026 thru 7/13/2026 South bound flow thru Potomac CS #2218 will be restored to 540,371dth.
Phase 2:
7/14/2026 thru 7/15/2026 North bound flow thru Sullivan CS #2113 will be reduced from 544,010dth to 0dth.
7/14/2026 thru 7/15/2026 South bound flow thru Potomac CS #2218 will be reduced from 540,371dth to 160,100dth.
MGT does anticipate an impact to firm transportation services. Demand charge credits will be applied pursuant to MGT's FERC Gas Tariff, General Terms and Conditions, Section 37.
Please contact your Commercial or Customer Service representative with questions.
TSP: 006792451
TSP Name: Midwestern Gas Transmission Company
Posting Date/Time: 06/05/2026 15:18:40
Notice Identifier: 176
Notice Stat Desc: Supersede
Notice Type Desc: Planned Service Outage
Notice Category: Critical
Subject: REVISED: Planned Service Outage – Flow through Sullivan CS#2113
Notice Eff Date/Time: 06/23/2026 09:00:00
Notice End Date/Time: 07/16/2026 09:00:00
Critical Desc: Yes
Notice Scope: TSP SPECIFIC
Reqrd Rsp Desc: No
Response Date/Time:
Prior Notice Identifier: 1525
Notice Text:
Due to planned maintenance between the Sullivan Compressor Station (CS) #2113 and Petersburg CS #2110 Midwestern Gas Transmission Company (MGT) will decrease capacity beginning Gas Day, Tuesday, June 23, 2026, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day, Wednesday, June 24, 2026.
Midwestern Gas Transmission Company (MGT) will again decrease capacity beginning Gas Day, Tuesday, July 14, 2026, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day, Wednesday, July 15, 2026.
Phase 1:
6/23/2026 – 6/24/2026 North bound flow thru Sullivan CS #2113 will be reduced from 544,010dth to 0dth.
6/23/2026 – 6/24/2026 South bound flow thru Sullivan CS #2113 will be reduced from 671,722dth to 160,100dth.
******
6/25/26 – 7/13/26 North bound flow thru Sullivan CS #2113 will be restored to 544,010dth.
6/25/26 – 7/13/26 South bound flow thru Sullivan CS #2113will be restored to 671,722dth.
******
Phase 2:
7/14/2026 - 7/15/2026 North bound flow through Sullivan CS #2113 will be reduced from 544,010dth to 0dth.
7/14/2026 - 7/15/2026 South bound flow through Sullivan CS #2113 will be reduced from 671,722dth to 160,100dth.
MGT does anticipate an impact to firm transportation services. Demand charge credits will be applied pursuant to MGT's FERC Gas Tariff, General Terms and Conditions, Section 37.
Please contact your Commercial or Customer Service representative with questions.
------------------------------------
Prior Notice ID: 171
Due to planned maintenance between the Sullivan Compressor Station (CS) #2113 and the Potomac Compressor Station (CS) #2118, Midwestern Gas Transmission Company (MGT) will decrease capacity beginning Gas Day, Tuesday, June 30, 2026, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day, Wednesday, July 01, 2026. Midwestern Gas Transmission Company (MGT) will again decrease capacity beginning Gas Day, Tuesday, July 14, 2026, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day, Wednesday, July 15, 2026.
Phase 1:
6/30/2026 thru 7/1/2026 North bound flow thru Sullivan CS #2113 will be reduced from 544,010dth to 0dth.
6/30/2026 thru 7/1/2026 South bound flow thru Potomac CS #2218 will be reduced from 540,371dth to 160,100dth.
7/2/2026 thru 7/13/2026 North bound flow thru Sullivan CS #2113 will be restored to 544,010dth.
7/2/2026 thru 7/13/2026 South bound flow thru Potomac CS #2218 will be restored to 540,371dth.
Phase 2:
7/14/2026 thru 7/15/2026 North bound flow thru Sullivan CS #2113 will be reduced from 544,010dth to 0dth.
7/14/2026 thru 7/15/2026 South bound flow thru Potomac CS #2218 will be reduced from 540,371dth to 160,100dth.
MGT does anticipate an impact to firm transportation services. Demand charge credits will be applied pursuant to MGT's FERC Gas Tariff, General Terms and Conditions, Section 37.
Please contact your Commercial or Customer Service representative with questions.
TSP Name: Midwestern Gas Transmission Company
Posting Date/Time: 06/05/2026 15:18:40
Notice Identifier: 176
Notice Stat Desc: Supersede
Notice Type Desc: Planned Service Outage
Notice Category: Critical
Subject: REVISED: Planned Service Outage – Flow through Sullivan CS#2113
Notice Eff Date/Time: 06/23/2026 09:00:00
Notice End Date/Time: 07/16/2026 09:00:00
Critical Desc: Yes
Notice Scope: TSP SPECIFIC
Reqrd Rsp Desc: No
Response Date/Time:
Prior Notice Identifier: 1525
Notice Text:
Due to planned maintenance between the Sullivan Compressor Station (CS) #2113 and Petersburg CS #2110 Midwestern Gas Transmission Company (MGT) will decrease capacity beginning Gas Day, Tuesday, June 23, 2026, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day, Wednesday, June 24, 2026.
Midwestern Gas Transmission Company (MGT) will again decrease capacity beginning Gas Day, Tuesday, July 14, 2026, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day, Wednesday, July 15, 2026.
Phase 1:
6/23/2026 – 6/24/2026 North bound flow thru Sullivan CS #2113 will be reduced from 544,010dth to 0dth.
6/23/2026 – 6/24/2026 South bound flow thru Sullivan CS #2113 will be reduced from 671,722dth to 160,100dth.
******
6/25/26 – 7/13/26 North bound flow thru Sullivan CS #2113 will be restored to 544,010dth.
6/25/26 – 7/13/26 South bound flow thru Sullivan CS #2113will be restored to 671,722dth.
******
Phase 2:
7/14/2026 - 7/15/2026 North bound flow through Sullivan CS #2113 will be reduced from 544,010dth to 0dth.
7/14/2026 - 7/15/2026 South bound flow through Sullivan CS #2113 will be reduced from 671,722dth to 160,100dth.
MGT does anticipate an impact to firm transportation services. Demand charge credits will be applied pursuant to MGT's FERC Gas Tariff, General Terms and Conditions, Section 37.
Please contact your Commercial or Customer Service representative with questions.
------------------------------------
Prior Notice ID: 171
Due to planned maintenance between the Sullivan Compressor Station (CS) #2113 and the Potomac Compressor Station (CS) #2118, Midwestern Gas Transmission Company (MGT) will decrease capacity beginning Gas Day, Tuesday, June 30, 2026, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day, Wednesday, July 01, 2026. Midwestern Gas Transmission Company (MGT) will again decrease capacity beginning Gas Day, Tuesday, July 14, 2026, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day, Wednesday, July 15, 2026.
Phase 1:
6/30/2026 thru 7/1/2026 North bound flow thru Sullivan CS #2113 will be reduced from 544,010dth to 0dth.
6/30/2026 thru 7/1/2026 South bound flow thru Potomac CS #2218 will be reduced from 540,371dth to 160,100dth.
7/2/2026 thru 7/13/2026 North bound flow thru Sullivan CS #2113 will be restored to 544,010dth.
7/2/2026 thru 7/13/2026 South bound flow thru Potomac CS #2218 will be restored to 540,371dth.
Phase 2:
7/14/2026 thru 7/15/2026 North bound flow thru Sullivan CS #2113 will be reduced from 544,010dth to 0dth.
7/14/2026 thru 7/15/2026 South bound flow thru Potomac CS #2218 will be reduced from 540,371dth to 160,100dth.
MGT does anticipate an impact to firm transportation services. Demand charge credits will be applied pursuant to MGT's FERC Gas Tariff, General Terms and Conditions, Section 37.
Please contact your Commercial or Customer Service representative with questions.