Great Lakes Gas Transmission Icon

MAINTENANCE SCHEDULE for Great Lakes Gas Transmission (Posted: 1/9/26)

Great Lakes Gas Transmission 1d ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP Name

Great Lakes Gas Transmission Limited Partnership

Notice ID

1133

TSP

046077343

Notice Eff Date:

01/09/2026

Posting Date/Time:

01/09/2026 09:20

Notice End Date:

04/01/2026

Critical:

Yes

Notice Eff Time:

09:20

Notice Type:

Plnd Outage

Notice End Time:

08:59

Notice Status:

Supersede

Required Response:

No response required

Prior Notice ID:

1108

Response Date/Time:

Subject

MAINTENANCE SCHEDULE for Great Lakes Gas Transmission (Posted: 1/9/26)

Message Text

Great Lakes Gas Transmission Maintenance Schedule has been updated.

 

Please refer to the maintenance schedule for the projected capacity impacts. Updated items are as follows:  

 

• Updated capacity impacts of scheduled winter digs and specific dates each for each dig section.

o Due to maintenance optimization, we have been able to reduce capacity impacts.

• Add - Shevlin Unit 303 Vibration Probe Repair 1/9 – 1/31 (No capacity impact)

• Updated the Firm Contract impact value to reflect the most updated contract level and fuel on the pipeline

 

Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 866-454-7572. 

TSP Name

Great Lakes Gas Transmission Limited Partnership

Notice ID

1133

TSP

046077343

Notice Eff Date:

01/09/2026

Posting Date/Time:

01/09/2026 09:20

Notice End Date:

04/01/2026

Critical:

Yes

Notice Eff Time:

09:20

Notice Type:

Plnd Outage

Notice End Time:

08:59

Notice Status:

Supersede

Required Response:

No response required

Prior Notice ID:

1108

Response Date/Time:

Subject

MAINTENANCE SCHEDULE for Great Lakes Gas Transmission (Posted: 1/9/26)

Message Text

Great Lakes Gas Transmission Maintenance Schedule has been updated.

 

Please refer to the maintenance schedule for the projected capacity impacts. Updated items are as follows:  

 

• Updated capacity impacts of scheduled winter digs and specific dates each for each dig section.

o Due to maintenance optimization, we have been able to reduce capacity impacts.

• Add - Shevlin Unit 303 Vibration Probe Repair 1/9 – 1/31 (No capacity impact)

• Updated the Firm Contract impact value to reflect the most updated contract level and fuel on the pipeline

 

Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 866-454-7572.