Zink Compressor Station Unplanned Maintenance 08-22-26 (Update 1)
Equitrans Gathering 1d ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
08-23-2026 15:30:00
Page 1 of 1
System Wide Notice Detail
TSP Name:
EUREKA
TSP:
Post Date/Time:
Sun Aug 23 15:30:00 GMT 2026
Subject:
Zink Compressor Station Unplanned Maintenance 08-22-26 (Update 1)
Notice Type:
CRITICAL
Notice ID:
43892
Prior Notice:
43891
43891
Notice Status Desc:
Supersede
Critical Desc:
Critical Notice
Notice Eff Date:
08-23-2026
Notice Eff Time:
15:30:00
Notice End Date:
11-30-2026
Notice End Time:
00:00:00
Required Response Indicator Description:
Notice Text:
Eureka Midstream LLC is providing notice that the unplanned maintenance at the Zink Compressor Station is continuing but an update to Capacity is
being made. Operationally Available capacity for the August 23rd ID2 cycle will be increased to a combined 250,000 DTH at the REX interconnect,
Meter #60059 (Eureka Cameron) .
Operationally Available capacity will be increased to a combined 305,000 DTH for the August 24th EVE cycle at the REX interconnect, Meter
#60059 (Eureka Cameron). Additionally, nominations and physical flow from Eureka Zink Compressor Station to the LXP Interconnect, Meter
#743103 (Eureka) will be restricted to 0 DTHS until further notice.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.

System Wide Notice Detail
TSP Name:
EUREKA
TSP:
Post Date/Time:
Sun Aug 23 15:30:00 GMT 2026
Subject:
Zink Compressor Station Unplanned Maintenance 08-22-26 (Update 1)
Notice Type:
CRITICAL
Notice ID:
43892
Prior Notice:
43891
43891
Notice Status Desc:
Supersede
Critical Desc:
Critical Notice
Notice Eff Date:
08-23-2026
Notice Eff Time:
15:30:00
Notice End Date:
11-30-2026
Notice End Time:
00:00:00
Required Response Indicator Description:
Eureka Midstream LLC is providing notice that the unplanned maintenance at the Zink Compressor Station is continuing but an update to Capacity is
being made. Operationally Available capacity for the August 23rd ID2 cycle will be increased to a combined 250,000 DTH at the REX interconnect,
Meter #60059 (Eureka Cameron) .
Notice Text:
Operationally Available capacity will be increased to a combined 305,000 DTH for the August 24th EVE cycle at the REX interconnect, Meter
#60059 (Eureka Cameron). Additionally, nominations and physical flow from Eureka Zink Compressor Station to the LXP Interconnect, Meter
#743103 (Eureka) will be restricted to 0 DTHS until further notice.