Zink Compressor Station Planned Maintenance Canceled [11-04-25] UPDATE II
Equitrans Gathering 4d ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
11-03-2025 00:00:00
Page 1 of 2
System Wide Notice Detail
TSP Name:
EUREKA
TSP:
Post Date/Time:
Mon Nov 03 00:00:00 GMT 2025
Subject:
Zink Compressor Station Planned Maintenance Canceled [11-04-25] UPDATE II
Notice Type:
CRITICAL
Notice ID:
43642
Prior Notice:
43621
43621
Notice Status Desc:
Supersede
Critical Desc:
Critical Notice
Notice Eff Date:
11-03-2025
Notice Eff Time:
00:00:00
Notice End Date:
02-03-2026
Notice End Time:
00:00:00
Required Response Indicator Description:
Notice Text:
Update to Notice ID #43627
Eureka Midstream LLS is providing notice that the planned maintenance at the Zink CS scheduled for the November 04, 2025, Gas Day has been
canceled.
Update to Notice ID #43621
Eureka Midstream LLC is providing notice that the planned maintenance previously scheduled for November 11, 2025, Gas Day at Zink Compressor
Station has been rescheduled to the November 04, 2025, Gas Day.
Original Notice (Revised)
Eureka Midstream LLC is providing notice of planned maintenance at Zink Compressor Station impacting deliveries to its downstream interconnects
on the November 04, 2025, Gas Day.
In conjunction with this maintenance, Operationally Available Capacity is reduced to a combined nomination total of 707,000 DTH at the REX
Interconnect, Meter #60059 (Eureka Cameron) and LXP Interconnect Meter #743103 for the November 04, 2025, Gas Day. All operators with
production flowing to Zink Compressor Station should expect to see higher than normal line pressure and a possible reduction in flow to receipts.
Nominations should be adjusted accordingly.
Nominations at Delivery Meter # 743103 (LXP-Eureka) from the EM-ORS Receipt IC (Meter # 10057) will not be impacted by this maintenance.
11-03-2025 00:00:00
Page 2 of 2
Nominations will be scheduled to not exceed the aforementioned amounts. These amounts are based on projected operating conditions and are
subject to change.
Should specific shut-ins be required, EQT Midstream will notify impacted parties.
Customers should monitor EQM Midstream Partners, LP – Gathering Informational Postings Website for updates to this notice.
*For production operations, Zink Compressor Station throughput will be reduced to 670 MMCFD for the November 04, 2025, Gas Day.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.

System Wide Notice Detail
TSP Name:
EUREKA
TSP:
Post Date/Time:
Mon Nov 03 00:00:00 GMT 2025
Subject:
Zink Compressor Station Planned Maintenance Canceled [11-04-25] UPDATE II
Notice Type:
CRITICAL
Notice ID:
43642
Prior Notice:
43621
43621
Notice Status Desc:
Supersede
Critical Desc:
Critical Notice
Notice Eff Date:
11-03-2025
Notice Eff Time:
00:00:00
Notice End Date:
02-03-2026
Notice End Time:
00:00:00
Required Response Indicator Description:
Update to Notice ID #43627
Eureka Midstream LLS is providing notice that the planned maintenance at the Zink CS scheduled for the November 04, 2025, Gas Day has been
canceled.
Update to Notice ID #43621
Eureka Midstream LLC is providing notice that the planned maintenance previously scheduled for November 11, 2025, Gas Day at Zink Compressor
Station has been rescheduled to the November 04, 2025, Gas Day.
Original Notice (Revised)
Eureka Midstream LLC is providing notice of planned maintenance at Zink Compressor Station impacting deliveries to its downstream interconnects
on the November 04, 2025, Gas Day.
Notice Text:
In conjunction with this maintenance, Operationally Available Capacity is reduced to a combined nomination total of 707,000 DTH at the REX
Interconnect, Meter #60059 (Eureka Cameron) and LXP Interconnect Meter #743103 for the November 04, 2025, Gas Day. All operators with
production flowing to Zink Compressor Station should expect to see higher than normal line pressure and a possible reduction in flow to receipts.
Nominations should be adjusted accordingly.
Nominations at Delivery Meter # 743103 (LXP-Eureka) from the EM-ORS Receipt IC (Meter # 10057) will not be impacted by this maintenance.
11-03-2025 00:00:00
Page 1 of 2
Nominations will be scheduled to not exceed the aforementioned amounts. These amounts are based on projected operating conditions and are
subject to change.
Should specific shut-ins be required, EQT Midstream will notify impacted parties.
Customers should monitor EQM Midstream Partners, LP – Gathering Informational Postings Website for updates to this notice.
*For production operations, Zink Compressor Station throughput will be reduced to 670 MMCFD for the November 04, 2025, Gas Day.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.
11-03-2025 00:00:00
Page 2 of 2