Construction and Maintenance Schedule Posting
Columbia Gas Transmission 1w ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TSP Name
Columbia Gas Transmission, LLC
TSP
054748041
Date
Time
Notice ID
26276048
Notice Type Description: Maintenance
Notice Stat Desc: Initiate
Prior Notice:
Critical: Y
Reqrd Rsp Desc: No Response Required
Post
Notice Effective
Notice End
Response
09/29/26
09/29/26
10/29/26
12:38:12 PM
4:00:00 AM
4:00:00 AM
Subject: Construction and Maintenance Schedule Posting
Author: John Whited
Notice Text
As a courtesy, Columbia Gas Transmission, LLC (TCO) hereby notifies customers the Construction and Maintenance Schedule posted under "Construction and Maintenance" on the Informational Postings website has been updated. TCO reminds customers to please check the Maintenance Schedule on a regular basis.The current schedule has been updated to reflect maintenance activity on the following: * Revised end date – TM17 Make Piggable Project – August 31 through October 24, 2026 (Previously scheduled to end on October 14, 2026)
* Revised end date – SM102 Pipe Replacement – September 30 through October 9, 2026 (Previously scheduled to end on October 7, 2026)
* October 27 through November 6, 2026 - TM17 Pigging
* October 30 through November 8, 2026 - WB Loop Pipeline maintenance between Cleveland CS and Files Creek CS
* December 7 through December 12, 2026 - MXP 100 Pipeline maintenanceAdditionally, the following file(s) can be located on Informational Postings under Construction and Maintenance
Columbia Gas Transmission, LLC
TSP
054748041
Date
Time
Notice ID
26276048
Notice Type Description: Maintenance
Notice Stat Desc: Initiate
Prior Notice:
Critical: Y
Reqrd Rsp Desc: No Response Required
Post
Notice Effective
Notice End
Response
09/29/26
09/29/26
10/29/26
12:38:12 PM
4:00:00 AM
4:00:00 AM
Subject: Construction and Maintenance Schedule Posting
Author: John Whited
Notice Text
As a courtesy, Columbia Gas Transmission, LLC (TCO) hereby notifies customers the Construction and Maintenance Schedule posted under "Construction and Maintenance" on the Informational Postings website has been updated. TCO reminds customers to please check the Maintenance Schedule on a regular basis.The current schedule has been updated to reflect maintenance activity on the following: * Revised end date – TM17 Make Piggable Project – August 31 through October 24, 2026 (Previously scheduled to end on October 14, 2026)
* Revised end date – SM102 Pipe Replacement – September 30 through October 9, 2026 (Previously scheduled to end on October 7, 2026)
* October 27 through November 6, 2026 - TM17 Pigging
* October 30 through November 8, 2026 - WB Loop Pipeline maintenance between Cleveland CS and Files Creek CS
* December 7 through December 12, 2026 - MXP 100 Pipeline maintenanceAdditionally, the following file(s) can be located on Informational Postings under Construction and Maintenance