Gas Quality Underperformance Update
Colorado Insterstate Gas 1mo ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Colorado Interstate Gas Company, L.L.C.
September 9, 2026
Gas Quality – Underperformance Update
Colorado
Interstate Gas Company, L.L.C. (CIG) previously posted (see Notice #123210 and updated Notice #123220) that if the
carbon dioxide (CO2) content at a number of CIG High Plains receipt locations
was not reduced to a level that is sufficient for CIG to meet the Wyoming
Interstate Company, L.L.C (WIC) maximum CO2 specification at the
(FLY) Flying Hawk interconnect, CIG will begin place underperformance caps on
these locations to reduce the CO2 content of the blended gas being
physically delivered to WIC to less than 2%.
While the CIG
tariff specification for CO2 is higher than WIC's, Section 3.1 of
the General Terms and Conditions (GT&C) of the Second Revised Volume No. 1
of CIG's FERC Gas Tariff (Tariff) provides, among other things, that CIG may
decline to receive Gas at any Point of Receipt if the quality of the Gas is
inferior to that “required by Shipper or a third Party at any Point of Delivery
under the Agreement," notwithstanding Sections 3.1 through 3.3 of the
GT&C of the Tariff.
CO2
content at the following locations has not been reduced to a level that is
sufficient for CIG to meet WIC's maximum CO2 specification.
Therefore, effective for the Intraday 1 Cycle, September 9, 2026 and the Timely
Cycle, September 10, 2026, CIG will continue placing underperformance caps on
the following locations to reduce the CO2 content of the blended gas
being physically delivered to WIC to less than 2%, until further notice.
|
Loc |
Loc Name |
Flow Dir |
Zone |
Segment |
County/ State |
Action |
|
49942 |
(JMC) JIM CREEK REC |
Rec |
04 |
244 |
WELD - CO |
Gas Quality Reduction |
|
47999 |
(LUC) LUCERNE REC |
Rec |
04 |
180 |
WELD - CO |
Gas Quality Reduction |
CO2 content at the following locations have improved and
underperformance caps at these locations will be cancelled effective for the
Intraday 1 Cycle, September 9, 2026 and the Timely Cycle, September 10, 2026,
CIG, but CIG will continue to monitor CO2 at these locations and
will reinstate caps if needed.
|
Loc |
Loc Name |
Flow Dir |
Zone |
Segment |
County/ State |
Action |
|
800360 |
(LAN) LANCASTER METER STATION |
Rec |
04 |
188 |
WELD - CO |
Cap Cancelled |
CIG will continue to monitor the CO2 content at these and other
locations, including (BOW) Bowie PIN #800104, and will provide updates if there
are any additions or deletions to the underperformance cap list.
|
Pipeline
Scheduling Hotline email CIGSched, or message KMRockiesSched on ICE Chat
|
Mike Burleson at (719) 640-1577 Hayden Garfield at (719) 726-5311 Matt Houtz at (719) 726-5230
|
Marketing questions
Contact your Marketing Representative. |
|
Rich Aten, Manager – Pipeline Scheduling Transportation and Storage Services Kinder Morgan Rockies Pipelines (719) 667-7527 or (719) 648-5253 richard_aten@kindermorgan.com | ICE Chat: raten
|
||
Colorado Interstate Gas Company, L.L.C.
September 9, 2026
Gas Quality – Underperformance Update
Colorado
Interstate Gas Company, L.L.C. (CIG) previously posted (see Notice #123210 and updated Notice #123220) that if the
carbon dioxide (CO2) content at a number of CIG High Plains receipt locations
was not reduced to a level that is sufficient for CIG to meet the Wyoming
Interstate Company, L.L.C (WIC) maximum CO2 specification at the
(FLY) Flying Hawk interconnect, CIG will begin place underperformance caps on
these locations to reduce the CO2 content of the blended gas being
physically delivered to WIC to less than 2%.
While the CIG
tariff specification for CO2 is higher than WIC's, Section 3.1 of
the General Terms and Conditions (GT&C) of the Second Revised Volume No. 1
of CIG's FERC Gas Tariff (Tariff) provides, among other things, that CIG may
decline to receive Gas at any Point of Receipt if the quality of the Gas is
inferior to that “required by Shipper or a third Party at any Point of Delivery
under the Agreement," notwithstanding Sections 3.1 through 3.3 of the
GT&C of the Tariff.
CO2
content at the following locations has not been reduced to a level that is
sufficient for CIG to meet WIC's maximum CO2 specification.
Therefore, effective for the Intraday 1 Cycle, September 9, 2026 and the Timely
Cycle, September 10, 2026, CIG will continue placing underperformance caps on
the following locations to reduce the CO2 content of the blended gas
being physically delivered to WIC to less than 2%, until further notice.
|
Loc |
Loc Name |
Flow Dir |
Zone |
Segment |
County/ State |
Action |
|
49942 |
(JMC) JIM CREEK REC |
Rec |
04 |
244 |
WELD - CO |
Gas Quality Reduction |
|
47999 |
(LUC) LUCERNE REC |
Rec |
04 |
180 |
WELD - CO |
Gas Quality Reduction |
CO2 content at the following locations have improved and
underperformance caps at these locations will be cancelled effective for the
Intraday 1 Cycle, September 9, 2026 and the Timely Cycle, September 10, 2026,
CIG, but CIG will continue to monitor CO2 at these locations and
will reinstate caps if needed.
|
Loc |
Loc Name |
Flow Dir |
Zone |
Segment |
County/ State |
Action |
|
800360 |
(LAN) LANCASTER METER STATION |
Rec |
04 |
188 |
WELD - CO |
Cap Cancelled |
CIG will continue to monitor the CO2 content at these and other
locations, including (BOW) Bowie PIN #800104, and will provide updates if there
are any additions or deletions to the underperformance cap list.
|
Pipeline
Scheduling Hotline email CIGSched, or message KMRockiesSched on ICE Chat
|
Mike Burleson at (719) 640-1577 Hayden Garfield at (719) 726-5311 Matt Houtz at (719) 726-5230
|
Marketing questions
Contact your Marketing Representative. |
|
Rich Aten, Manager – Pipeline Scheduling Transportation and Storage Services Kinder Morgan Rockies Pipelines (719) 667-7527 or (719) 648-5253 richard_aten@kindermorgan.com | ICE Chat: raten
|
||