TSP/TSP Name:  6914865-COLORADO INTERSTATE GAS CO. Critical: Y Notice Type Desc (1):  GAS QUALITY Notice Type Desc (2):  ISSUES Notice Eff Date/Time:  09/08/2026 10:46:09AM Notice End Date/Time:  09/09/2026 9:00:00am Post Date/Time:  9/8/2026 10:46:09 AM Notice ID: 123220 Reqrd Rsp:  1 Rsp Date/Time:  9/8/2026 12:00:00 AM Notice Stat Desc:  SUPERSEDE Prior Notice:  123210 Subject:  Gas Quality - Underperformance
Notice Text:

Colorado Interstate Gas Company, L.L.C.  

September 8, 2026 

Gas Quality - Underperformance 

Colorado Interstate Gas Company, L.L.C. (CIG) previously posted (see Notice #123210) that if the carbon dioxide (CO2) content at a number of CIG High Plains receipt point was not reduced to a level that is sufficient for CIG to meet the Wyoming Interstate Company, L.L.C (WIC) maximum CO2 specification at the (FLY) Flying Hawk interconnect by the Timely Cycle, September 9, 2026, CIG will begin place underperformance caps on these locations to reduce the CO2 content of the blended gas being physically delivered to WIC to less than 2%. 

While the CIG tariff specification for CO2 is higher than WIC's, Section 3.1 of the General Terms and Conditions (GT&C) of the Second Revised Volume No. 1 of CIG's FERC Gas Tariff (Tariff) provides, among other things, that CIG may decline to receive Gas at any Point of Receipt if the quality of the Gas is inferior to that “required by Shipper or a third Party at any Point of Delivery under the Agreement," notwithstanding Sections 3.1 through 3.3 of the GT&C of the Tariff.   

CO2 content at the following locations has not been reduced to a level that is sufficient for CIG to meet WIC's maximum CO2 specification.  Therefore, effective for the Timely Cycle, September 9, 2026, CIG will be placing underperformance caps on these locations to reduce the CO2 content of the blended gas being physically delivered to WIC to less than 2%, until further notice. 

Loc 

Loc Name 

Flow Dir 

Zone 

Segment 

County/ State 

Action 

49942 

(JMC) JIM CREEK REC 

Rec 

04 

244 

WELD - CO 

Gas Quality Reduction 

47999 

(LUC) LUCERNE REC 

Rec 

04 

180 

WELD - CO 

Gas Quality Reduction 

800360 

(LAN) LANCASTER METER STATION 

Rec 

04 

188 

WELD - CO 

Gas Quality Reduction 

 
CIG will continue to monitor the CO2 content at these and other locations, including (BOW) Bowie PIN #800104, and will provide updates if there are any additions or deletions to the underperformance cap list. 
 

 
Scheduling questions or concerns 

 

 Pipeline Scheduling Hotline  
(800) 238-3764 option 2, 

email CIGSched, or message  
KMRockiesSched on ICE Chat. 

 

 

Operational issues or concerns 
 
Mike Burleson at (719) 640-1577 

Hayden Garfield at (719) 726-5311 

or Matt Houtz at (719) 726-5230  

Marketing questions 

 

 Contact your Marketing Representative. 

 

Rich Aten, Manager – Pipeline Scheduling 

Transportation and Storage Services 

Kinder Morgan Rockies Pipelines 

(719) 667-7527 or (719) 648-5253 

richard_aten@kindermorgan.com 

 

TSP/TSP Name:  6914865-COLORADO INTERSTATE GAS CO. Critical: Y Notice Type Desc (1):  GAS QUALITY Notice Type Desc (2):  ISSUES Notice Eff Date/Time:  09/08/2026 10:46:09AM Notice End Date/Time:  09/09/2026 9:00:00am Post Date/Time:  9/8/2026 10:46:09 AM Notice ID: 123220 Reqrd Rsp:  1 Rsp Date/Time:  9/8/2026 12:00:00 AM Notice Stat Desc:  SUPERSEDE Prior Notice:  123210 Subject:  Gas Quality - Underperformance
Notice Text:

Colorado Interstate Gas Company, L.L.C.  

September 8, 2026 

Gas Quality - Underperformance 

Colorado Interstate Gas Company, L.L.C. (CIG) previously posted (see Notice #123210) that if the carbon dioxide (CO2) content at a number of CIG High Plains receipt point was not reduced to a level that is sufficient for CIG to meet the Wyoming Interstate Company, L.L.C (WIC) maximum CO2 specification at the (FLY) Flying Hawk interconnect by the Timely Cycle, September 9, 2026, CIG will begin place underperformance caps on these locations to reduce the CO2 content of the blended gas being physically delivered to WIC to less than 2%. 

While the CIG tariff specification for CO2 is higher than WIC's, Section 3.1 of the General Terms and Conditions (GT&C) of the Second Revised Volume No. 1 of CIG's FERC Gas Tariff (Tariff) provides, among other things, that CIG may decline to receive Gas at any Point of Receipt if the quality of the Gas is inferior to that “required by Shipper or a third Party at any Point of Delivery under the Agreement," notwithstanding Sections 3.1 through 3.3 of the GT&C of the Tariff.   

CO2 content at the following locations has not been reduced to a level that is sufficient for CIG to meet WIC's maximum CO2 specification.  Therefore, effective for the Timely Cycle, September 9, 2026, CIG will be placing underperformance caps on these locations to reduce the CO2 content of the blended gas being physically delivered to WIC to less than 2%, until further notice. 

Loc 

Loc Name 

Flow Dir 

Zone 

Segment 

County/ State 

Action 

49942 

(JMC) JIM CREEK REC 

Rec 

04 

244 

WELD - CO 

Gas Quality Reduction 

47999 

(LUC) LUCERNE REC 

Rec 

04 

180 

WELD - CO 

Gas Quality Reduction 

800360 

(LAN) LANCASTER METER STATION 

Rec 

04 

188 

WELD - CO 

Gas Quality Reduction 

 
CIG will continue to monitor the CO2 content at these and other locations, including (BOW) Bowie PIN #800104, and will provide updates if there are any additions or deletions to the underperformance cap list. 
 

 
Scheduling questions or concerns 

 

 Pipeline Scheduling Hotline  
(800) 238-3764 option 2, 

email CIGSched, or message  
KMRockiesSched on ICE Chat. 

 

 

Operational issues or concerns 
 
Mike Burleson at (719) 640-1577 

Hayden Garfield at (719) 726-5311 

or Matt Houtz at (719) 726-5230  

Marketing questions 

 

 Contact your Marketing Representative. 

 

Rich Aten, Manager – Pipeline Scheduling 

Transportation and Storage Services 

Kinder Morgan Rockies Pipelines 

(719) 667-7527 or (719) 648-5253 

richard_aten@kindermorgan.com