TSP/TSP Name:  6914865-COLORADO INTERSTATE GAS CO. Critical: Y Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE Notice Eff Date/Time:  06/22/2026 2:49:51PM Notice End Date/Time:  06/23/2026 9:00:00am Post Date/Time:  6/22/2026 2:49:51 PM Notice ID: 123089 Reqrd Rsp:  1 Rsp Date:  6/22/2026 12:00:00 AM Notice Stat Desc:  SUPERSEDE Prior Notice:  123084 Subject:  Operations Planning Report V2 July 2026
Notice Text:

Colorado Interstate Gas Company

Operations Planning Report July 2026

Reissued June 22, 2026

Pipe

Start Date

End Date

County, ST

Scheduling Location

Maintenance List

Base Capacity (Dth)

Reduction (Dth)

Net (Dth)

Flow Indication

Update

CIG

7/6/26

7/11/26

SWEETWATER, WY

106_(KDWC) KANDA WEST

Addition
Line 5A Scheduled Remediation Digs

326,000

326,000

0

TD1

Update

CIG

7/6/26

7/11/26

SWEETWATER, WY

106_(KDWC) KANDA WEST

Addition
Line 5A Scheduled Remediation Digs

180,000

180,000

0

TD2

Update

CIG

7/6/26

7/11/26

SWEETWATER, WY

800282 NW P/L/CIG (GRN) GREEN RIVER NPC ST

Addition
Line 5A Scheduled Remediation Digs

221,600

221,600

0

R

Update

CIG

7/6/26

7/11/26

SWEETWATER, WY

800282 NW P/L/CIG (GRN) GREEN RIVER NPC ST

Addition
Line 5A Scheduled Remediation Digs

188,600

188,600

0

D

Update

CIG

7/8/26

7/9/26

RIO BLANCO, CO

800167_ PSCC/CIG (CRG) CORRAL GULCH RIO BLA

Corral Gulch Meter Station - Meter Maintenance

79,000

79,000

0

D

CIG

7/15/26

7/15/26

SWEETWATER, WY

895008_MGR/CIG (TAB) TABLE ROCK MASTER MET

Table Rock Station DOT/ESD Test

5,000

3,000

2,000

R

CIG

7/21/26

7/23/26

SWEETWATER, WY

110_(BXEC) BAXTER EAST_BH

Wamsutter Station DOT/ESD Test

265,000

138,000

127,000

TD2

CIG

7/21/26

7/21/26

PARK,WY

142_(BHNC) BIG HORN NORTH

Elk Basin Station DOT/ESD Test

117,000

117,000

0

TD1

CIG

7/21/26

7/21/26

PARK,WY

142_(BHNC) BIG HORN NORTH_BH

Elk Basin Station DOT/ESD Test

90,000

30,000

60,000

TD2

CIG

7/22/26

7/22/26

PARK,WY

142_(BHNC) BIG HORN NORTH

Elk Basin Unit Shut Down Checks

117,000

62,000

55,000

TD1

CIG

7/22/26

7/22/26

PARK,WY

142_(BHNC) BIG HORN NORTH_BH

Elk Basin Unit Shut Down Checks

90,000

13,000

77,000

TD2

CIG

7/1/26

7/31/26

LARAMIE,WY

164_(CHWC) CHEYENNE WEST

Notice of Force Majeure – Segment 164
Reference Updated Notice# 122918
Line 5A pipeline Cheyenne to Laramie investigation and repair

570,000

223,000

347,000

TD1

CIG

7/1/26

7/31/26

LARAMIE,WY

164_(CHWC) CHEYENNE WEST_BH

Notice of Force Majeure – Segment 164
Reference Updated Notice# 122918
Line 5A pipeline Cheyenne to Laramie investigation and repair

315,000

80,000

235,000

TD2

In addition to planned outages, this report reflects the repairs and maintenance being performed related to Force Majeure events.

Due to the nature of such events, the dates for the associated repairs and maintenance of those events are assumed to extend until the end of the month.

These repairs and maintenance, however, may extend beyond the end of the month including beyond the current year.

More information on these repairs and maintenance will be posted as a Critical Notice under the Notices section of the Informational Postings tab on the CIG Electronic Bulletin Board

TSP/TSP Name:  6914865-COLORADO INTERSTATE GAS CO. Critical: Y Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE Notice Eff Date/Time:  06/22/2026 2:49:51PM Notice End Date/Time:  06/23/2026 9:00:00am Post Date/Time:  6/22/2026 2:49:51 PM Notice ID: 123089 Reqrd Rsp:  1 Rsp Date:  6/22/2026 12:00:00 AM Notice Stat Desc:  SUPERSEDE Prior Notice:  123084 Subject:  Operations Planning Report V2 July 2026
Notice Text:

Colorado Interstate Gas Company

Operations Planning Report July 2026

Reissued June 22, 2026

Pipe

Start Date

End Date

County, ST

Scheduling Location

Maintenance List

Base Capacity (Dth)

Reduction (Dth)

Net (Dth)

Flow Indication

Update

CIG

7/6/26

7/11/26

SWEETWATER, WY

106_(KDWC) KANDA WEST

Addition
Line 5A Scheduled Remediation Digs

326,000

326,000

0

TD1

Update

CIG

7/6/26

7/11/26

SWEETWATER, WY

106_(KDWC) KANDA WEST

Addition
Line 5A Scheduled Remediation Digs

180,000

180,000

0

TD2

Update

CIG

7/6/26

7/11/26

SWEETWATER, WY

800282 NW P/L/CIG (GRN) GREEN RIVER NPC ST

Addition
Line 5A Scheduled Remediation Digs

221,600

221,600

0

R

Update

CIG

7/6/26

7/11/26

SWEETWATER, WY

800282 NW P/L/CIG (GRN) GREEN RIVER NPC ST

Addition
Line 5A Scheduled Remediation Digs

188,600

188,600

0

D

Update

CIG

7/8/26

7/9/26

RIO BLANCO, CO

800167_ PSCC/CIG (CRG) CORRAL GULCH RIO BLA

Corral Gulch Meter Station - Meter Maintenance

79,000

79,000

0

D

CIG

7/15/26

7/15/26

SWEETWATER, WY

895008_MGR/CIG (TAB) TABLE ROCK MASTER MET

Table Rock Station DOT/ESD Test

5,000

3,000

2,000

R

CIG

7/21/26

7/23/26

SWEETWATER, WY

110_(BXEC) BAXTER EAST_BH

Wamsutter Station DOT/ESD Test

265,000

138,000

127,000

TD2

CIG

7/21/26

7/21/26

PARK,WY

142_(BHNC) BIG HORN NORTH

Elk Basin Station DOT/ESD Test

117,000

117,000

0

TD1

CIG

7/21/26

7/21/26

PARK,WY

142_(BHNC) BIG HORN NORTH_BH

Elk Basin Station DOT/ESD Test

90,000

30,000

60,000

TD2

CIG

7/22/26

7/22/26

PARK,WY

142_(BHNC) BIG HORN NORTH

Elk Basin Unit Shut Down Checks

117,000

62,000

55,000

TD1

CIG

7/22/26

7/22/26

PARK,WY

142_(BHNC) BIG HORN NORTH_BH

Elk Basin Unit Shut Down Checks

90,000

13,000

77,000

TD2

CIG

7/1/26

7/31/26

LARAMIE,WY

164_(CHWC) CHEYENNE WEST

Notice of Force Majeure – Segment 164
Reference Updated Notice# 122918
Line 5A pipeline Cheyenne to Laramie investigation and repair

570,000

223,000

347,000

TD1

CIG

7/1/26

7/31/26

LARAMIE,WY

164_(CHWC) CHEYENNE WEST_BH

Notice of Force Majeure – Segment 164
Reference Updated Notice# 122918
Line 5A pipeline Cheyenne to Laramie investigation and repair

315,000

80,000

235,000

TD2

In addition to planned outages, this report reflects the repairs and maintenance being performed related to Force Majeure events.

Due to the nature of such events, the dates for the associated repairs and maintenance of those events are assumed to extend until the end of the month.

These repairs and maintenance, however, may extend beyond the end of the month including beyond the current year.

More information on these repairs and maintenance will be posted as a Critical Notice under the Notices section of the Informational Postings tab on the CIG Electronic Bulletin Board