Carolina Gas Transmission Icon

Mainline Work 14-010 to 14-005 - Update

Carolina Gas Transmission 2mo ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Critical Desc
Critical notice

Notice ID
4714

Subject
Mainline Work 14-010 to 14-005 - Update

Notice Type
Maintenance

Post D/T
8/11/2026 9:53:00 AM CCT

Notice Eff D/T
8/11/2026 9:53:00 AM CCT

Notice End D/T
9/2/2026 9:53:00 AM CCT

Notice Stat Desc
Supersede (a previous situation is being amended/updated)

Prior Notice
4706

Reqrd Rsp Desc
No response required

TSP
09-499-2187

TSP Name
Carolina Gas Transmission, LLC

Notice Text

As noted in Notice 4706, Carolina Gas Transmission (CGT) is conducting scheduled mainline maintenance of 6.3 miles of 8" line between Stations 14-010 in Lee County, SC and 14-005 in Kershaw County, SC. The work was initially expected to be completed by August 14, 2026; however, the completion date has been extended and is now anticipated for August 26, 2026.

Based on current operating conditions, this outage is not anticipated to affect firm transportation services; however, impacts to secondary firm transportation and interruptible services are possible. For additional information, please contact your CGT Customer Service Representative or Account Executive.



Attachments
No Attachments

Critical Desc
Critical notice

Notice ID
4714

Subject
Mainline Work 14-010 to 14-005 - Update

Notice Type
Maintenance

Post D/T
8/11/2026 9:53:00 AM CCT

Notice Eff D/T
8/11/2026 9:53:00 AM CCT

Notice End D/T
9/2/2026 9:53:00 AM CCT

Notice Stat Desc
Supersede (a previous situation is being amended/updated)

Prior Notice
4706

Reqrd Rsp Desc
No response required

TSP
09-499-2187

TSP Name
Carolina Gas Transmission, LLC

Notice Text

As noted in Notice 4706, Carolina Gas Transmission (CGT) is conducting scheduled mainline maintenance of 6.3 miles of 8" line between Stations 14-010 in Lee County, SC and 14-005 in Kershaw County, SC. The work was initially expected to be completed by August 14, 2026; however, the completion date has been extended and is now anticipated for August 26, 2026.

Based on current operating conditions, this outage is not anticipated to affect firm transportation services; however, impacts to secondary firm transportation and interruptible services are possible. For additional information, please contact your CGT Customer Service Representative or Account Executive.