LIFTED NOTICE OF FORCE MAJEURE ANR Pipeline Company - Bridgman Compressor Station impacting the Michigan Leg North and South (Lifted: 3/19/25)

ANR Pipeline Company 1mo ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP
006958581

TSP Name
ANR Pipeline Company

Notice Type Desc
Force Maj

Posting Date/Time
03/19/2025 9:55 am

Notice Effective Date/Time
03/19/2025 9:55 am

Notice End Date/Time
03/20/2025 8:59 am

Notice ID
12260

Notice Status Desc
Supersede

Prior Notice
12258

Reqrd Rsp
5

Rsp Date/Time


Subject
LIFTED NOTICE OF FORCE MAJEURE ANR Pipeline Company - Bridgman Compressor Station impacting the Michigan Leg North and South (Lifted: 3/19/25)

Notice Text
LIFTED NOTICE OF FORCE MAJEURE ANR Pipeline Company - Bridgman Compressor Station impacting the Michigan Leg North and South (Lifted: 3/19/25)


Effective immediately, ANR is lifting the Force Majeure at Bridgman Northbound and St. John Eastbound. Capacity will be reinstated as follows:

Bridgman Northbound (LOC #226632) reinstated to 1363 MMcf/d
St. John Eastbound (LOC #226633) reinstated to 1325 MMcf/d.

Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267


TSP
006958581

TSP Name
ANR Pipeline Company

Notice Type Desc
Force Maj

Posting Date/Time
03/19/2025 9:55 am

Notice Effective Date/Time
03/19/2025 9:55 am

Notice End Date/Time
03/20/2025 8:59 am

Notice ID
12260

Notice Status Desc
Supersede

Prior Notice
12258

Reqrd Rsp
5

Rsp Date/Time


Subject
LIFTED NOTICE OF FORCE MAJEURE ANR Pipeline Company - Bridgman Compressor Station impacting the Michigan Leg North and South (Lifted: 3/19/25)

Notice Text
LIFTED NOTICE OF FORCE MAJEURE ANR Pipeline Company - Bridgman Compressor Station impacting the Michigan Leg North and South (Lifted: 3/19/25)


Effective immediately, ANR is lifting the Force Majeure at Bridgman Northbound and St. John Eastbound. Capacity will be reinstated as follows:

Bridgman Northbound (LOC #226632) reinstated to 1363 MMcf/d
St. John Eastbound (LOC #226633) reinstated to 1325 MMcf/d.

Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267