Reminder Planned Service Outage – Maintenance Project 24.031 May 5 2025
Adelphia Gateway 1d ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
March 18, 2025
Planned Service Outage – Maintenance Project 24.031
Impact Area – Zone South Locations
Outage Dates: May 5, 2025 thru May 12, 2025
As a supplement to the previously posted maintenance summary for Project 24.031, under Planned Service Outages
on the informational postings site, Adelphia Gateway, LLC (“Adelphia”), is providing additional clarification of
restrictions.
The current schedule for this maintenance project is May 5, 2025, through May 12, 2025, with an anticipated return
to service of 9:00 AM CPT on May 12, 2025.
As a result of this work, the operational available capacity at the following locations will be set to zero at 9:00 AM
CPT with the start of gas day May 5, 2025.
ZONE
LOCATION NAME
DIRECTION OF FLOW
OPERATIONAL
AVAILABLE CAPACITY
South
TM-South Transfer
Receipt
0
South
Tetco West Rockhill
Receipt
0
South
Col-Claymont
Delivery
0
South
Transco Ridge
Delivery
0
South
Peco-Tilghman
Delivery
0
The current schedule for this planned service outage and its anticipated impacts are subject to change, so please
monitor critical notices, including the Adelphia’s Planned Outage and Maintenance Summary on Info Posts for any
updates to this project or others.
Contact your Transportation or Marketing Services Representative.
March 18, 2025
Planned Service Outage – Maintenance Project 24.031
Impact Area – Zone South Locations
Outage Dates: May 5, 2025 thru May 12, 2025
As a supplement to the previously posted maintenance summary for Project 24.031, under Planned Service Outages
on the informational postings site, Adelphia Gateway, LLC (“Adelphia”), is providing additional clarification of
restrictions.
The current schedule for this maintenance project is May 5, 2025, through May 12, 2025, with an anticipated return
to service of 9:00 AM CPT on May 12, 2025.
As a result of this work, the operational available capacity at the following locations will be set to zero at 9:00 AM
CPT with the start of gas day May 5, 2025.
OPERATIONAL
ZONE
LOCATION NAME
DIRECTION OF FLOW
AVAILABLE CAPACITY
South
TM-South Transfer
Receipt
0
South
Tetco West Rockhill
Receipt
0
South
Col-Claymont
Delivery
0
South
Transco Ridge
Delivery
0
South
Peco-Tilghman
Delivery
0
The current schedule for this planned service outage and its anticipated impacts are subject to change, so please
monitor critical notices, including the Adelphia’s Planned Outage and Maintenance Summary on Info Posts for any
updates to this project or others.