Natural Gas Pipeline Notice 46401
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
| TSP/TSP Name: 6931794-NATURAL GAS PIPELINE CO. | Critical: Y |
| Notice Type Desc (1): FORCE MAJEURE | Notice Type Desc (2): FORCE MAJEURE |
| Notice Eff Date/Time: 10/17/2025 4:17:26PM | Notice End Date/Time: 10/18/2025 9:00:00am |
| Post Date/Time: 10/17/2025 4:17:26 PM | Notice ID: 46401 |
| Reqrd Rsp: 1 | Rsp Date: 10/17/2025 |
| Notice Stat Desc: TERMINATE | Prior Notice: 46398 |
| Subject: FORCE MAJEURE - REMEDIATION - CS 341-P2 |
FORCE MAJEURE – GULF COAST MAINLINE SOUTH OF CS 341– PIPELINE REMEDIATION – PHASE 2 POSTPONED
Phase 2 has been postponed due to unforeseen additional permitting requirements. Therefore, effective on the dates noted below, the point listed below in Phase 2 is available for service. All transport services are available. See previous Notice ID 46398 dated October 16, 2025.
Phase 2 Available Points – The following receipt and delivery point will be available effective for gas day Tuesday, October 21, 2025, Timely Cycle and continuing thereafter:
LOC 3886 BANHUB/NGPL BANQUETE HUB BI-DI
Continue to monitor Natural's interactive website for any future updates. Please contact your Account Director or Scheduling Representative if you have any questions.
| TSP/TSP Name: 6931794-NATURAL GAS PIPELINE CO. | Critical: Y |
| Notice Type Desc (1): FORCE MAJEURE | Notice Type Desc (2): FORCE MAJEURE |
| Notice Eff Date/Time: 10/17/2025 4:17:26PM | Notice End Date/Time: 10/18/2025 9:00:00am |
| Post Date/Time: 10/17/2025 4:17:26 PM | Notice ID: 46401 |
| Reqrd Rsp: 1 | Rsp Date: 10/17/2025 |
| Notice Stat Desc: TERMINATE | Prior Notice: 46398 |
| Subject: FORCE MAJEURE - REMEDIATION - CS 341-P2 |
FORCE MAJEURE – GULF COAST MAINLINE SOUTH OF CS 341– PIPELINE REMEDIATION – PHASE 2 POSTPONED
Phase 2 has been postponed due to unforeseen additional permitting requirements. Therefore, effective on the dates noted below, the point listed below in Phase 2 is available for service. All transport services are available. See previous Notice ID 46398 dated October 16, 2025.
Phase 2 Available Points – The following receipt and delivery point will be available effective for gas day Tuesday, October 21, 2025, Timely Cycle and continuing thereafter:
LOC 3886 BANHUB/NGPL BANQUETE HUB BI-DI
Continue to monitor Natural's interactive website for any future updates. Please contact your Account Director or Scheduling Representative if you have any questions.