TSP/TSP Name:  6931794-NATURAL GAS PIPELINE CO. Critical: Y
Notice Type Desc (1):  FORCE MAJEURE Notice Type Desc (2):  FORCE MAJEURE
Notice Eff Date/Time:  10/16/2025 4:32:41PM Notice End Date/Time:  10/17/2025 9:00:00am
Post Date/Time:  10/16/2025 4:32:41 PM Notice ID: 46398
Reqrd Rsp:  1 Rsp Date:  10/16/2025
Notice Stat Desc:  SUPERSEDE Prior Notice:  46393
Subject:  FORCE MAJEURE - REMEDIATION - CS 341 -P1
Notice Text:

FORCE MAJEURE – GULF COAST MAINLINE SOUTH OF CS 341– PIPELINE REMEDIATION – PHASE 1 POSTPONED

 

Phase 1 has been postponed due to unforeseen additional permitting requirements.  Therefore, effective for gas day Friday, October 17, 2025, Evening Cycle and continuing thereafter, all points listed below in Phase 1 are available to resume flow.  All transport services are available.  Currently, there are no changes to Phase 2 and the impact will remain as noted below.  See previous Notice ID 46393 dated October 15, 2025.

 

As posted on Natural's Outage Impact Report (X23-1238605 and X25-950254), as part of its ongoing pipeline Integrity Management Program and the results of an ILI tool run on Natural's GC #1 mainline south of Compressor Station 341 (CS 341) located in Segment 20 of the South Texas Zone, Natural has discovered anomalies at various locations that require pipeline remediation.  This is a Force Majeure event.

 

As a result, Natural is required to shut in sections of the GC #1 mainline and shut in the following locations during this remediation.  Transport services for receipt and deliveries at the locations listed below will be unavailable during this outage.  No transport services will be available until the work has been completed.  As noted below, the impact to Phase 1 has been changed.   

 

Phase 1 Available Points - The following receipt and delivery points are available effective for gas day Friday, October 17, 2025, Evening Cycle and continuing thereafter:

 

LOC 3107       KMTEJAS/NGPL #2 JIM HOGG

LOC 24001     ETP/NGPL THOMPSONVILLE JIM HOGG

LOC 25259     LOBO/NGPL KING RANCH KLEBERG

LOC 53776     VCP/NGPL MUSTANG M/L 1 NUECES

LOC 54849     WHISTLEP/NGPL WHISTLE REC NUECES

LOC 900436    TRIN GAS/NGPL SEJITA DUVAL

LOC 900439    DCP OPER/NGPL LA GLORIA JIM WELLS

LOC 900532    HPL/NGPL JIM HOGG

LOC 905572    DCP INTR/NGPL THOMPSONVILLE JIM HOG

 

Phase 2 Unavailable Points – The following receipt and delivery point will be unavailable beginning gas day Tuesday, October 21, 2025, Timely Cycle and anticipated to continue through gas day Monday, October 27, 2025:

 

LOC 3886        BANHUB/NGPL BANQUETE HUB BI-DI

 

Continue to monitor Natural's interactive website for any updates to this remediation work.  Please contact your Account Director or Scheduling Representative if you have any questions.

TSP/TSP Name:  6931794-NATURAL GAS PIPELINE CO. Critical: Y
Notice Type Desc (1):  FORCE MAJEURE Notice Type Desc (2):  FORCE MAJEURE
Notice Eff Date/Time:  10/16/2025 4:32:41PM Notice End Date/Time:  10/17/2025 9:00:00am
Post Date/Time:  10/16/2025 4:32:41 PM Notice ID: 46398
Reqrd Rsp:  1 Rsp Date:  10/16/2025
Notice Stat Desc:  SUPERSEDE Prior Notice:  46393
Subject:  FORCE MAJEURE - REMEDIATION - CS 341 -P1
Notice Text:

FORCE MAJEURE – GULF COAST MAINLINE SOUTH OF CS 341– PIPELINE REMEDIATION – PHASE 1 POSTPONED

 

Phase 1 has been postponed due to unforeseen additional permitting requirements.  Therefore, effective for gas day Friday, October 17, 2025, Evening Cycle and continuing thereafter, all points listed below in Phase 1 are available to resume flow.  All transport services are available.  Currently, there are no changes to Phase 2 and the impact will remain as noted below.  See previous Notice ID 46393 dated October 15, 2025.

 

As posted on Natural's Outage Impact Report (X23-1238605 and X25-950254), as part of its ongoing pipeline Integrity Management Program and the results of an ILI tool run on Natural's GC #1 mainline south of Compressor Station 341 (CS 341) located in Segment 20 of the South Texas Zone, Natural has discovered anomalies at various locations that require pipeline remediation.  This is a Force Majeure event.

 

As a result, Natural is required to shut in sections of the GC #1 mainline and shut in the following locations during this remediation.  Transport services for receipt and deliveries at the locations listed below will be unavailable during this outage.  No transport services will be available until the work has been completed.  As noted below, the impact to Phase 1 has been changed.   

 

Phase 1 Available Points - The following receipt and delivery points are available effective for gas day Friday, October 17, 2025, Evening Cycle and continuing thereafter:

 

LOC 3107       KMTEJAS/NGPL #2 JIM HOGG

LOC 24001     ETP/NGPL THOMPSONVILLE JIM HOGG

LOC 25259     LOBO/NGPL KING RANCH KLEBERG

LOC 53776     VCP/NGPL MUSTANG M/L 1 NUECES

LOC 54849     WHISTLEP/NGPL WHISTLE REC NUECES

LOC 900436    TRIN GAS/NGPL SEJITA DUVAL

LOC 900439    DCP OPER/NGPL LA GLORIA JIM WELLS

LOC 900532    HPL/NGPL JIM HOGG

LOC 905572    DCP INTR/NGPL THOMPSONVILLE JIM HOG

 

Phase 2 Unavailable Points – The following receipt and delivery point will be unavailable beginning gas day Tuesday, October 21, 2025, Timely Cycle and anticipated to continue through gas day Monday, October 27, 2025:

 

LOC 3886        BANHUB/NGPL BANQUETE HUB BI-DI

 

Continue to monitor Natural's interactive website for any updates to this remediation work.  Please contact your Account Director or Scheduling Representative if you have any questions.